SECOND PHARMACY PRODUCTION BUILDING IN CHINA

Since in the meridian of July the second pharmacy production building for China is prefabricated in the ADK plant in Neresheim. The total floor area of the 2 story building possesses 3.258 qm and consists of 77 modules. They are complete installed and equipped. Manufactured according to Good Manufacturing Practice (GMP) and Chinese standards China Compulsory Certification (CCC) made in Germany.

The prefabrication will be finished mid-September. Then follows a 6 week lasting transport on road and sea to the destination point a biopark in China.

After the final assembly of the already complete equipped modules can the pharmacy building get in operation at the beginning of Novemder.

The total building time has been taken then 5 Months. This cannot be realized on site.

We will inform you further with interesting details and pictures during the next weeks.

 