WITH A CONSTRUCTION CRANE OVER AN EXISTING BUILDING

Planned with maximum performance for the Diakonie-Klinikum Stuttgart.
In a courtyard that was rebuilt from all sides, the extension of the Diakonie-Klinikum in Stuttgart had to take place. It was not only the limited storage options for building materials that posed a problem. The modules, weighing up to 23 tonnes, had to be lifted above the existing building, which made previous statistical studies and assessments of a disaster inescapable.
Without disruption of the hospital operation, the increase could be completed on schedule and successfully.
Modules
Area
Levels
Construction time on site
59
11.592 m²
2,5
3 months